Paralos Energy Live News

Paralos Energy delivers to Siemens Gamesa the BoP works for four (4) Wind Farms of total capacity 76MW in several areas of Greece.

23/10/2020

The long-term and successful cooperation between Siemens Gamesa and Paralos Energy was continued with the award of four (4) Wind Farms of total capacity 76MW in several areas of Greece, to Paralos Energy.

The four projects, of total capacity 76MW, located in different areas of Greece were the following:

  • 16MW Wind Farm “Kali Chitsa”, located at Etoloakarnania, Greece
  • 24MW Wind Farm “Litharoserma”, located at Nafpaktia, Greece
  • 18MW Wind Farm “Kefalaria”, located at Fokida, Greece
  • 18MW Wind Farm “Flamouria”, located at Kozani, Greece

The scope of works for Paralos Energy for the first three (3) projects was the complete Balance of Plant works including access roads, plarforms, Wind Turbine’s foundations, MV cables networks, Control Buildings, HV Substations while for the fourth project the scope of works was limited to the electrical works.

After the Projects’ construction and set to operation, they were handed over to Siemens Gamesa maintenance dept. and were included to the maintenance Frame Agreement between Siemens Gamesa and Paralos Energy.