Projects

Construction of 16MW Wind Farm Kali Chitsa

Engineering, Procurement & Construction (EPC) of Balance of Plant (BoP) of a 16MW Wind Farm (8 Wind Turbine Generators, Gamesa G114T80), including a 32km underground and overhead interconnection MV line and a 33/150kV 40/50MVA substation

Location
Astakos and Etoliko, Etolia&Akarnania, Greece
Year
2020
Client
Siemens Gamesa Renewable Energy

Project Description

EPC of BoP of a 16MW Wind Farm and a 33/150kV 40/50MVA substation

  • Engineering ,Design of Civil & Electrical Systems of the Wind Farm
  • Construction of roads and platforms
  • Improvement of access roads
  • Construction of 8 WTG foundations
  • Supply of MV, FO cables and earthing conductor
  • Construction of internal network and of 32km of overhead and underground interconnection MV line
  • Supply and installation of MV control building including the MV and LV equipment and materials
  • Testing & commissioning
  • Start Up
  • Engineering ,Design of Civil & Electrical Systems of the substation
  • Permitting from IPTO
  • Supply of Power Transformer, HV, MV and LV equipment and materials
  • Construction of concrete bases and steel structures for the equipment of the switchyard
  • Construction of the substation Control Building
  • Erection of the HV equipment / Power Transformer
  • Testing & commissioning
  • Start Up

Other Projects

  • Dervenochoria, Viotia, Greece
  • 2023
  • Iberdrola Group
  • Bekrevenikos, Kozani, Greece
  • 2022
  • Juwi Hellas S.A.
  • Petroussa, Drama, Greece
  • 2022
  • Wonderplant SA