Engineering, Procurement & Construction (EPC) of Balance of Plant (BoP) of a 6.8MW Wind Farm (8 Wind Turbine Generators, Gamesa G52T55), including a 15km overhead interconnection MV line
Location
Pylos, Messinia, Greece
Year
2013
Client
Gamesa S.A
Project Description
EPC of BoP of a 6.8 MW Wind Farm including:
Engineering, Design of Civil & Electrical Systems of the Wind Farm
Construction of roads and platforms
Improvement of access roads
Construction of 8 WTG foundations
Supply of MV, FO cables and earthing conductor
Construction of internal network and of 15km of overhead interconnection MV line
Supply and installation of MV control building including the MV and LV equipment and materials